2018 is looking to be a busy year for us. In November last year began working with Sir Robert McAlpine on two student accommodation blocks in St Andrews – Agnes Blackadder Hall and University Hall. Between the two blocks, there are 391 apartments. We will be erecting the SFS frames for both buildings, then moving into Agnes Blackadder to install the partitions.

Our relationship with Dandara continues, as in December, we commenced work on their Summerhill Road apartments in Aberdeen. Smaller than Mugiemoss, Summerhill Road comprises of 26 apartments. We are looking forward to working on further projects with Dandara.

We are excited to be working with Cala Homes this year. Last month we begin on site at Henderson House, Gullane. This is a refurbishment of the old Fire Service Training Station, converting it into 22 units, a mixture of apartments and duplexes. In March, work kicks off on their new build development behind Donaldson’s College, Edinburgh. This crescent shaped structure comprises of 84 units, a mixture of apartments and penthouses.

March also means work begins with McCarthy & Stone and their retirement development in Inverness. The timber frame building consists of 50 apartments. We look forward to developing a relationship with them.

We are continuing work on Shrubhill with Allenbuild. As Block A continues, work also starts on Blocks B and F later this year. We are pleased with our progression on this site and are looking forward to future work with Allebuild.