Engine Yard

Client: Allenbuild (Places for People)

Size of Contract: £1,075,000.00

Sector: Drylining, Ceilings & Subfloor

Duration of Project: 31 Weeks

 

Services provided:

Acoustic & Thermal Insulation Applications

Metal Stud Partitioning

Acoustic & Architectural Ceiling Systems

Steel Frame Systems

Drywall Installation

Metal Frame Ceiling Systems

Project Description

On behalf of Places for People (Allenbuild) Ltd we helped to create over fifty build-to-rent apartments within 2 apartment blocks. We were delighted to work on both the internal partitions and ceilings packages & the raised Danskin floor package.

Despite this project commencing during the beginning of the Covid-19 pandemic, our strong supplier relationships ensured that we managed material supply to deliver programme continuity against a backdrop of material shortages and allocation from suppliers.